Federal Ministry of Works (FMW)
... building the backbone for Development ...
Follow Us:
Welcome To Federal Ministry Of Works.
Minister Federal Ministry Of Works Engr. David Umahi.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Road Inspection.
Road Construction Inspection Tour.
Road Inspection.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Feb
06
2026

LATEST PRESS

FG ACTS ON PUBLIC COMPLAINTS, ISSUES TOUGH DIRECTIVES TO CHINA HARBOUR ON ROAD PROJECTS

The Federal Government has taken decisive steps to address public complaints and enforce contractor accountability following a high-level meeting between the Minister of Works, Senator Engineer David Umahi, CON, FNSE, FNATE, officials of the Ministry and those of China Harbour Engineering Company (CHEC) and its sister company, China Harbour Operation and Maintenance Company (CHOMC), concessionaires on the Mararraba-Keffi-Akwanga-Lafia-Makurdi Dual Carriageway, held on Thursday, 5 February, 2026 at the Ministry’s Headquarters, Abuja.

During the meeting, several concerns relating to CHEC and CHOMC’s projects were reviewed, and firm warnings and directives were issued to safeguard public health, ensure quality delivery, and sustainability, also to protect government investment.

Engr. Umahi disclosed that the Ministry received a formal petition over the ongoing Makurdi-9th Nile-Enugu road project, where excessive dust from construction activities has continued to pose environmental and health risks to residents on the corridor. Therefore, he directed that the Permanent Secretary issue a letter to the contractor, mandating immediate dust-control measures, including soil stabilisation techniques, to be implemented. He warned that failure to resolve the issue within 7 days would lead to the project's suspension.

On the Dualisation of the Mararraba-Keffi-Akwanga-Lafia-Makurdi Road, the Minister stated that although the project was started by the previous government, the present one completed some sections and tolled them. It was, however, observed that portions of the earlier completed road by the past administration were already falling. Consequently, he reiterated his previous directive that the first five (5) kilometres of the project must be milled, re-asphalted with concrete, and properly re-marked, stressing that the contractor has been given seven days to commence the work.

He further directed that other identified failed sections along the Dual Carriageway be properly rehabilitated through milling and overlay, with particular attention given to poorly executed areas around the Nasarawa State University, failed bridge expansion joints, damaged manhole covers, blocked drainage channels, washouts, and constant vegetation control. In addition, he instructed that all road furnishings be reinstated after the maintenance works.

Engr. Umahi emphasised the need for improved highway safety management, directing the contractor to strengthen corridor monitoring and ensure the prompt removal of stationary vehicles to prevent obstruction and accidents on the Highways.

Whilst expressing deep concern over the slow pace of work on the 7th Axial Road project in Lagos, he noted that site mobilisation remains insufficient despite repeated engagements with the contractor at the site and in Abuja. He highlighted that substantial mobilisation funds have already been paid to CHEC, yet key machineries have not been deployed with minimal site clearance being carried out. In this regard, he also warned that “If full mobilisation is not achieved within the agreed timeframe, we will recover the funds and take firm contractual action.”

The Minister made it abundantly clear that the Renewed Hope Administration of His Excellency, President Bola Ahmed Tinubu, GCFR will no longer tolerate poor execution, delays, or disregard for agreed standards, stressing that warning letters, withholding of certificates, and broader contractual consequences will be applied, where necessary.

He assured Nigerians that the Federal Government remains responsive to public concerns and committed to protecting lives, infrastructure integrity, and getting value for public funds. He informed that President Tinubu is determined to enforce accountability and break away from practices that undermine national development.

Highlighting the administration’s inheritance of projects, Engr. Umahi stated that the government inherited 2,064 ongoing projects valued at more than ₦13 trillion as of May 29, 2023, excluding those on the Infrastructure Tax Credit Scheme. Despite funding constraints, road construction and rehabilitation are progressing nationwide, he confirmed. While acknowledging that the entire federal road network cannot be completed within a single term of four years, the Minister expressed confidence that sustained tempo over the next five years would significantly transform Nigeria’s infrastructure. He, therefore, urged Nigerians to massively vote for President Tinubu in 2027, in order to continue enhancing infrastructure and transportation as enablers of growth and much more.

Responding on behalf of the  management of the two companies, the Acting Executive Director (Operations) of CHOMC, Mr. Stephen Lee promised that industry-standard anti-dust measures will be taken on all construction sites, adequate mobilisation and full commencement of work on the 7th Axial 
Road and the rehabilitation of the failed sections of the Mararraba-Lafia road.
 
The Minister concluded by reiterating that contractors must either meet agreed standards or face firm consequences, as the Federal Government remains resolute in delivering safe and durable road infrastructure to Nigerians.


 

Oct
18
2020

After Emergency Repairs By FG, Fashola Approves Reopening Of Eko, Marine Bridges On Monday * Minister thanks Lagosians for their patience, understanding, cooperation   * First Phase completed while work commences immediately on the Second Phase After concluding urgently needed repair works on Eko and Marine Bridges in Lagos, the Minister of Works and Housing, Mr. Babatunde Fashola, SAN, has directed that both bridges be reopened to traffic on Monday, October 19, 2020. The approval for the reopening of the completed First Phase of the repairs on the Bridges by midnight on Sunday 18th of October, which was given by the Minister on Friday was sequel to the report by the Contractor handling the projects, Messrs. Buildwell Plant & Equipment Industries Limited that the repair works on the First Phase had been completed 100 percent. In his directives for the reopening of the Bridges, Fashola thanked Lagosians for their patience, understanding and cooperation while sections of the Bridges were closed also directed that members of the public should be informed of any restrictions to traffic while work is ongoing on the Second Phase of the project. The Minister added that while the completed section of the Eko Bridge (Lagos Island Bound) should be reopened to traffic, work should commence immediately on the Alaka Bound side of the project. Explaining further on the next phase of repair works on the Bridges, the Director Highways (Bridges & Designs) in the Ministry, Engr. Emmanuel Adeoye, said work was taking off without the need for either partial or complete closure of the Bridges, adding, however , that the public would be informed adequately should such a step become necessary. The 1,350 metre Eko Bridge, built in phases between 1965 and 1975, links the Lagos Island to the Mainland. It was closed to traffic in March this year in order to replace faulty joints and bearings. But, as a result of COVID-19 lockdown, actual repair works commenced in the first week of June. Work commenced in May on the first of the three phases in which repair works on the Marine Bridge was divided. The repairs on the Bridge, which is part of a network of complex bridges with several loops taking traffic in and out of the Apapa area of Lagos, included jacketing and skin repairs of the piers, lifting the bridge section deck in order to change the electrometric bearing, milling and placing a new wearing course of asphalt among others. The repair works on the Eko and Marine Bridges is part of the ongoing Federal Government’s Bridge Maintenance Programme which involves the repairs and rehabilitation of over 37 bridges nationwide with a substantial number already completed while others are at different stages of completion. ...

Oct
09
2020

Gombe – Yola Road Receiving Attention - FG The attention of the Honourable Minister of State, Federal Ministry of Works and Housing Engr. Abubakar D Aliyu, FNSE has been drawn to the publication on the social media on the failed portion of Gombe-Yola road. The Federal Ministry of Works and Housing (FMW&H) is aware of the condition of the road and committed to repairs of the damaged portion. The portion had been adequately assessed, redesigned and procurement process completed as an additional work to the subsisting contract for the rehabilitation of the road and FEC has approved. The bad portion which is about 11km sits on clay soil called black cotton soil which cannot support traffic. The removal and replacement of this black cotton soil was not part of the original contract, but approval has been given by FEC to augment the contract to include the removal of the black cotton soil and replacement with stones and laterite. However, the contractor cannot embark on the removal of this clay until after the raining season. In the interim, the contractor is carrying out palliative works to keep the road motorable. The contractor is on site working even now. The contract awarded involves massive excavation of the soil and replacement with stones to make the road last long. We therefore appeal for patience and understanding of the citizens and other road users. Full re construction of the bad section on the road will commence as soon as the rains subsides. It needs no restating that President Muhammadu Buhari is committed to alleviating the pains of Nigerians wherever they reside. ...

Oct
07
2020

Repairs on Murtala Muhammed Bridge: FG Assures of Timely Completion The Federal Government has assured road users that the repairs on Murtala Muhammed Bridge along Kotonkarfe - Lokoja road will be completed on schedule despite the challenges caused by the corona virus and the rise in the tide of the River Niger. The assurance was given by the Director of Highways and Bridges in the Federal Ministry of Works and Housing, Engineer Emmanuel Adetunji Adeoye who was at the site to access the progress of work on the bridge. The Director said, “ Before the rains came, around May and June they did a lot of under water works and at that time the public was not noticing.” “Because the water has come up now and they cannot really do much of the underwater works, that’s why they are doing the surface work that everyone is seeing but when we get towards November and December they will go on to continue the underwater works”. Looking at the time and the work they have done so far, I believe they are still within the schedule.” Engineer Adeoye added that although the contract was awarded on the 10th of March, 2020 but due to the Covid 19 pandemic, work commenced on the 11th of May, 2020 and the work is expected to be completed by 10th May, 2022. He appealed to the public to show understanding and be patient as government was committed to the repair of the bridge. The Director said, “My appeal to road users is they should be patient and know that government is committed to the repair of the bridge.” He advised people to follow the instructions of the security personnel on ground so as to enjoy free flow of traffic. The representative of the Contractor Engineer Ebenezer Princewill said the company, Hallekem Limited was prepared to deliver the contract within schedule as long as funds were provided. On local content he said available local materials were being used while most of the workers were from within the area. He said, “In this community we are training people on the project. We are also empowering the youths and have employed about thirty Nigerians for the job.” ...

First First First

LIVE ACTIVITY FEED

PUBLIC ANNOUNCEMENT


Nov
03
2025

  


PHOTO NEWS

Jun
02
2025

DRIVING NIGERIA’S FUTURE: CELEBRATING TWO YEARS OF TRANSFORMATIVE LEADERSHIP AND THE LAGOS-CALABAR COASTAL HIGHWAY MILESTONE

DRIVING NIGERIA’S FUTURE: CELEBRATING TWO YEARS OF TRANSFORMATIVE LEADERSHIP AND THE LAGOS-CALABAR COASTAL HIGHWAY MILESTONE

Click To View More Pictures

PHOTO NEWS

Apr
28
2025

MID -TERM REVIEW MEETING ON THE IMPLIMENTATION OF THE DECISIONS REACHED AT THE 29TH NATIONAL COUNCIL ON WORKS (NCW) DAY 1

MID -TERM REVIEW MEETING ON THE IMPLIMENTATION OF THE DECISIONS REACHED AT THE 29TH NATIONAL COUNCIL ON WORKS (NCW) DAY 1

Click To View More Pictures