Federal Ministry of Works (FMW)
... building the backbone for Development ...
Follow Us:
Welcome To Federal Ministry Of Works.
Minister Federal Ministry Of Works Engr. David Umahi.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Road Inspection.
Road Construction Inspection Tour.
Road Inspection.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Feb
12
2026

LATEST PRESS

FG PUSHES AHEAD WITH STRATEGIC ROAD PROJECTS IN BORNO DESPITE SECURITY CHALLENGES

The Federal Ministry of Works has restated its avowed intention to rehabilitate the Maiduguri–Monguno Road (Section I) in Borno State, as work progresses steadily despite prevailing security and logistical challenges.

As the nationwide media tour of the North East Zone continues, the Federal Controller of Works in the State, Engr. Salihu Adamu assured Nigerians that the project will be completed despite persistent security and logistical constraints. “The biggest challenge faced by the contractor is insecurity. There are pockets of attacks on the highways, and this has forced them to take longer and safer routes to source construction materials,” he stated, while addressing the media at the project site in Maiduguri.

The project was initially awarded in 2018 to QUMECS (Nigeria) Limited at a contract sum of ₦21.73 billion, traversing 105.6 kilometres. Following a technical review and scope adjustment, the project was revised to incorporate a flexible pavement structure with asphaltic concrete shoulders, bringing the current contract sum to ₦28.37 billion to reflect prevailing realities and enhanced engineering specifications.

Phase 1 of the project covers 30 kilometres. Significant progress has been recorded, with approximately 5.8 kilometres completed up to binder course level and about 8 kilometres of stone base executed. Clearance works have also extended beyond 15 kilometres, while shoulder construction is ongoing, in line with the Ministry’s revised policy, which replaces surface dressing with asphaltic concrete shoulders to provide stronger structural protection for the carriageway and enhanced pavement durability.

As security remains the major constraint on the Maiduguri–Monguno corridor, Borno State continues to operate under emergency conditions, with base and sub-base laterite sourced from Ngamdu near the Yobe State border (about 150 km away). And stone materials hauled from as far as Shira town in Bauchi State (approximately 450 km) due to restricted access and security considerations like the ban on the blasting of rocks in the state.

The Project Manager for the company, Engr. Bukar Kadai, confirmed that the contractor remains fully mobilised on site with two active teams handling shoulder construction and stone base operations simultaneously, while asphalt laying is scheduled to commence following the delivery of bitumen to the site, soon.

Also speaking on the same project, the Chairman of the Nigerian Society of Engineers (NSE), Maiduguri Branch, Engr. Mohammed Shettima expressed satisfaction with the quality of work, stating that the rehabilitation will ease transportation challenges for residents and road users.

In another vein, the Chairman of the Nigeria Union of Journalists (NUJ), Borno State Council, Abdulkarim Haruna, inaugurated the completed Limited Rehabilitation of Kaga–Gubio Road, Sections I and II outside Benisheik Town, on behalf of the Honourable Minister of Works, Engr. David Umahi, CON, FNSE, FNATE. He described the road as a strategic one for economic empowerment and social inclusion. He stated, “Roads are a means of empowering the people. This road connecting to Benisheik, which serves as a gateway to Maiduguri and Yobe state, is a very positive development.” He further urged the media to continue sensitising Nigerians on ongoing infrastructure reforms and national development efforts of the administration of President Bola Ahmed Tinubu, GCFR.

The FCW described the Kaga–Gubio Road as a critical intervention, facilitating the movement of agricultural produce into Maiduguri and other parts of the zone, strengthening commercial activities within the corridor. He explained that the project forms part of a broader emergency and special works designed to safeguard existing infrastructure, improve mobility, and support economic stability in areas facing security challenges.
 

Mar
06
2017

FG Waives Payment Of 10% Equity On Mortgages Below 5 Million Naira 1.         As a demonstration of its resolute commitment to the provision of affordable housing to Nigerians, especially the low income earners, the Federal Government has graciously approved that henceforth mortgages below N5m (five million naira) will not attract the initial payment of 10% equity from offtakers. 2.        This was made known by the Minister of State for Power, Works and Housing, Hon. Mustapha Baba Shehuri while commissioning a 125- unit Housing Estate being financed by the Federal Mortgage Bank of Nigeria (FMBN) and  developed by a private developer, Messrs LCK Projects (Nigeria) Limited, in Enugu, Enugu State, recently. 3.        Hon. Baba Shehuri stated that in view of the challenge of housing deficit in Nigeria, which has been put at 16 – 17 million, the Ministry plans to build mass houses in every state of the Federation for public workers and other interested parties, over the next three years, using the instructmentality of Public-Private Partnerships. 4.        He added that National Housing Models have been designed and approved for each geo-political zone, which takes care of our cultural and climatic diversities in our choice of house type and standardization in the use of local building materials. This will translate to affordability of housing for Nigerians and will also create employment opportunities for our teaming youths that are currently roaming the streets. 5.        While commending the effort of the apex mortgage bank, the Minister noted that it has a pivotal role to play in the actualization of the aspirations of many Nigerians to own a home through mortgage, adding that the Muhammadu Buhari’s led administration will lend its full support to the Federal Mortgage Bank of Nigeria  towards ensuring that it is adequately recapitalized and repositioned  to cater for the mortgage finance needs of Nigerian workers, who would be the major beneficiaries of houses built under the National Housing Programme. 6.        Earlier in his address at the Commissioning Ceremony, the Executive Governor of Enugu State, RT Hon. Ifeanyi Ugwuanyi assured the Minister of the readiness of the State to continue providing enabling environment for housing development to thrive. 7.        The Minister was also at Abakaliki, Ebonyi State, where he commissioned the 1st set of  72 units of  houses out of 240  being financed by FMBN and undertaking by the Ebonyi State Housing Development Corporation (ESHDC). He was also at Owerri, Imo State for the commissioning of a 100-unit FMBN-Minfa Housing Estate. 8.        The Ebonyi State Executive Governor, His Excellency Dave Umahi reiterated the willingness of the government to partner with the Bank in the provision of affordable housing for its workers, especially, and the citizenry, in general. He added that the completed buildings have already been allocated to Civil/Public servants through the Office of the State Head of Service on Owner-Occupier basic. 9.        His Excellency, the Executive Governor of Imo State, Owelle Rochas Okorocha, CFR, represented by the Deputy Governor, His Excellency, Prince Eze Madumere, MFR, urged the management of FMBN to replicate the gesture in the 27 Local Government Areas of the State, while informing the Minister that a Committee, to be chaired by his humble self is to be constituted immediately to drive the process. 10.      The Acting Managing Director of Federal Mortgage Bank Nigeria, Mr. Richard Esin, while calling on other Nigerians, in private employment or self employed, who are currently not contributing to the National Housing Fund (NHF), to key in. He further disclosed that the commissioned Housing Estates and others to be commissioned soon across the length and breadth of Nigeria were funded from the lean resources of the NHF, an SPV for driving the aspirations of Nigerians to transit from being tenants to home owners. ...

Mar
06
2017

Power Sector Liquidity: FG Commits N702 Billion To Nbet To Meet Payment Obligations * Says it is part of its Economic Growth and Recovery Plan to take the nation out of recession * It is in recognition of the critical role that energy and access to electricity play in economic growth and poverty reduction – FG * Subsequent interventions to strengthen financial transparency and discipline, attain and sustain generation, transmission and distribution above 4,000 MWh/h, among others As a first step towards solving the debilitating liquidity problem in the Power Sector, the Federal Government is committing up to N702 Billion to the Nigerian Bulk Electricity Trading (NBET) to enable it meet its payment obligations to Generation Companies (GenCos) on a more regular basis to ensure delivery of electricity across the country The commitment under the “Payment Guarantee Support to NBET”, scheme takes retrospective effect from January, 2017 and would enable the government-owned NBET to pay its obligations to the GenCos and through them to their gas and equipment suppliers, banks and other partners. According to a Communiqué issued Friday by the Ministry of Power, Works and Housing, the Federal Government intervention, which represents a critical element of its Economic Growth and Recovery Plan, is part of the far-reaching steps taken by the Federal Executive Council (FEC) on Wednesday, March 1, 2017, to reset the electricity industry in view of “the critical role that energy and access to electricity play in economic growth and poverty reduction”. It is also to provide payment assurance to electricity generation companies, improve financial liquidity in the power and banking sectors and ensure the provision of electricity to households and businesses to boost economic growth, job and wealth creation, the Communiqué said. Recalling that the Commissioners of the Nigerian Electricity Regulatory Commission (NERC) was recently inaugurated to provide government with “the requisite legal and regulatory framework to implement its credible recovery programme,” the Communiqué said the steps, “conceived within a sequence of sector reforms”, represented Government’s commitment to enforcing decisions taken as a nation to move from a wholly Government-owned to private sector led electricity industry. “These steps, conceived within a sequence of sector reforms, confirm Government’s commitment to enforcing decisions taken as a nation to move from a vertically integrated Government owned statutory monopoly that did not serve our power needs, to a private sector led industry-with Government as guarantor, regulator and policy maker–that achieves the objective of developing a better and sustainable power sector as quickly as possible”, the Communiqué said. Assuring that Government, in collaboration with NERC, would continue to work with the DisCos to improve their payment performance from the current 24.9 per cent level, with the 100 per cent target, the Communiqué said subsequent complementary interventions would seek to strengthen financial transparency and discipline to ensure that all industry revenues were fairly distributed to all market participants and their suppliers according to contractual commitments. Subsequent interventions, the Communiqué also said, would seek to achieve and exceed the contracted and committed ATC&C loss targets and sustain aggregate collection efficiency above 60 per cent as well as secure adequate capitalization and liquidity to ensure that all market participants, particularly those upstream of the DisCos, were paid according to contracts and were adequately funded to sustain and expand their operations. Other objectives subsequent Government interventions would seek to achieve include attaining and sustaining generation, transmission and distribution above 4,000 MWh/h delivered to customers, from lowest cost base load GenCos by deploying and/or facilitating new generation using all available energy sources. Government will also seek to recover lost gas supply, add new gas supply, and complete transmission projects curtailing generation particularly in the eastern part of the national grid, the Communiqué said adding that through wider consultation, government would implement a simplified tariff methodology that would accurately reflect market realities, exchange rate realities, and the cost of producing and delivering electricity. Acknowledging, however, that the plans alone would not solve all the problems of the Power Sector, the Communiqué said they were, however, conceived “within a package of measures” to ensure that the electricity system continued on a steady trajectory of growth, better service delivery and a climate where investors who played by the rules set by NERC and deliver results that benefit the consuming public were compensated appropriately. It recalled that NERC licensed eleven distribution companies (DisCos) to distribute and sell electricity with the Private Sector owning 60 per cent while Government retained 40 per cent shares of the companies adding that Government also established NBET, 100 owned by it, to buy electricity in bulk from electricity generating companies (GenCos) licensed to produce electricity. “The intention was that while the DisCos take the time necessary to improve and expand their networks of substations and lines, enumerate and meter their customers, buy additional power directly from GenCos and provide better customer services, the existing and new GenCos could confidently make investments to expand generation with assurance that the bulk buyer would pay them for the electricity they deliver”, it further explained adding that Government retained ownership, for the time being, of the transmission system used to transmit the electricity from the GenCos to the DisCos. It said, however that the DisCos have not improved customer services at the pace Government and the country would expect and also were not paying fully for the electricity they received from the GenCos through NBET adding, however, that some of the reasons for the failure were not the fault of the DisCos alone. According to the Communiqué, “Regulatory and tariff inconsistencies of the past administration, unexpected changes in the foreign exchange market, and lower than expected generation due largely to pipeline vandalization for example, have challenged the DisCos’ ability to perform. But much of the failure relates to their inadequate financial and technical capacity and some sharp practices of the DisCos in their administration of collections from customers”. Explaining the reason for government intervention, the Communiqué said as a result of the aforementioned inadequacies, NBET’s monthly collection from the DisCos was not enough to pay NBET's contractual obligation to the GenCos resulting to huge government debts adding that in recent months the payment by the DisCos to NBET was as low as 17.0 per cent of NBET's invoice. “In January 2017, it was 24.9 per cent. The GenCos in turn do not pay their gas suppliers, equipment suppliers, banks and other partners what they are contractually bound to pay. The DisCos also do not pay TCN what is contractually due to it for transmitting the energy the DisCos sell to consumers”, it said adding that these had resulted in payment shortfalls with the accumulated debts increasingly threatening the electricity supply system and undermining the growth of the economy and the electricity sector. The Communiqué read in part, “In recognition of the critical role that energy and access to electricity plays in economic growth and poverty reduction, the Federal Government of Nigeria (FGN) as part of its Economic Growth and Recovery Plan, at its Federal Executive Council meeting of 1st March 2017 has taken far-reaching steps to reset the electricity industry”. “These steps, conceived within a sequence of sector reforms, confirm Government’s commitment to enforcing decisions taken as a nation to move from a vertically integrated Government owned statutory monopoly that did not serve our power needs, to a private sector led industry –with Government as guarantor, regulator and policy maker–that achieves the objective of developing a better and sustainable power sector as quickly as possible” ...

Mar
06
2017

FG Assures Nigerians On Road Development The Minister of Power, Works and Housing, Babatunde Raji Fashola, has reiterated Federal Government commitment to road development nationwide. Fashola gave the assurance at a World Press Conference, on the closure of Abuja International Airport for the runway rehabilitation at Obasanjo Hall, Federal Secretariat, Phase II, Bullet House, Abuja. The Minister said though the contract for rehabilitation of Abuja-Kaduna road is on course, the Federal Government had to intervene with the emergency repairs of the road as a result of the closure of the Abuja International Airport runway which makes the Kaduna Airport an alternative. The conference was organized by the Federal Ministry of Information and Culture and in attendance were the Miniter of Information and Culture, Alhaji Lai Muhammed; Minister of Transport, Rotimi Amechi; Minister of Aviation, Alhaji Hadi Sariki; and Inspector-General of Police, Idris Ibrahim Kpotum. The Minister of Power, Works and Housing, was represented by the Director, Highways (Rehabilitation and Construction), Engr. Yemi Oguntominiyi. ...

First First First

LIVE ACTIVITY FEED

PUBLIC ANNOUNCEMENT


Nov
03
2025

  


PHOTO NEWS

Jun
02
2025

DRIVING NIGERIA’S FUTURE: CELEBRATING TWO YEARS OF TRANSFORMATIVE LEADERSHIP AND THE LAGOS-CALABAR COASTAL HIGHWAY MILESTONE

DRIVING NIGERIA’S FUTURE: CELEBRATING TWO YEARS OF TRANSFORMATIVE LEADERSHIP AND THE LAGOS-CALABAR COASTAL HIGHWAY MILESTONE

Click To View More Pictures

PHOTO NEWS

Apr
28
2025

MID -TERM REVIEW MEETING ON THE IMPLIMENTATION OF THE DECISIONS REACHED AT THE 29TH NATIONAL COUNCIL ON WORKS (NCW) DAY 1

MID -TERM REVIEW MEETING ON THE IMPLIMENTATION OF THE DECISIONS REACHED AT THE 29TH NATIONAL COUNCIL ON WORKS (NCW) DAY 1

Click To View More Pictures